RJB industrial machinery relocation specialists installations decommisions heavy machinery equipment relocations Southampton Hampshire
heavy machinery relocation Southampton Hampshire
+44 (0)1489 559091
enquiries@rjbprojects.co.uk
heavy machinery relocation Southampton Hampshire

RJB Projects - Machinery Movers & Machinery Relocations Southampton Hampshire

Installations, Decommissions and Relocations of Heavy Machinery - UK & Worldwide Machinery Movers

Case Studies


Click the plus signs to read the detail of our case studies.


Scope of work:

The relocation of complete production lines incorporating different production machinery from conveyors, wrappers, cartoners, labellers and case sealers, from Auburn, Maine, USA to Portsmouth, Hampshire UK. We worked side by side with the customer's project manager from the early stages of the project, to plan and organise every aspect of the job including timescales, loading plans, transportation and health and safety.

While the machinery was still in operation an auditing team flew out to establish the condition of the lines and make notes for spares required for refurbishment. The auditing team then took vital timings and measurements to use as a bench mark when installing the machinery. Once the audit was complete the rest of the team flew out and the lines were handed over. Once the lines were handed over they were disassembled in a methodical manner. Rather than disassembling the complete units, two 10m steel frames were manufactured to pick two of the units off the line. This reduced time considerably. Both production lines were vacuum sealed and packed into 30 wooden crates, which were then loaded into ten 40ft sea containers and shipped to the UK. RJB managed all of the exportation and importation documentation to allow the production lines to be delivered to the site in the UK on time.

Once at the new site, the lines where installed in parallel to their existing foot print. Due to the voltage and frequency difference between the USA and the UK a 50HZ conversion was under taken of both lines this entailed changing most motors and transformers.

The lines then had their final checks:

  • Static and Dynamic Checks
  • Yellow Lining
  • Input Output Checks

Once all of these tasks had been undertaken successfully the line had a 5 minute shakedown, to check rotation on the motors and also to see whether any of the components had come loose in transit. After the shakedown a full 1 hour dry run was undertaken, monitoring the lines for:

  • Voltage
  • Motor & Gearbox temperatures
  • Current
  • Heater temperatures

After the 1 hour dry run was completed the line was handed over to the customer.

heavy machinery relocation Southampton Hampshire
40 ton fork truck
heavy machinery relocation Southampton Hampshire
Unloading of 30 ton press

Scope of work:

The relocation of a seal manufacturer from Southampton to Derby and fit out the new site with a chilled water system, compressed air ring main and power to all the machinery. A total of 36 machines were moved and the project took 6 weeks including the site services. Working with the customers project manager we were able to offer a complete turn key project.

A 300M 75mm diameter ABS plastic chilled water ring main and a 300M 50mm diameter galvanised air ring main were installed at 4 meters from the floor level. To keep cost to a minimum the routes of the pipe work were directed over the proposed location of each machine, this also allowed the cable tray to be fitted from the same fixings. The chilled water and compressed air circuits were commission tested and full documentation issued to verified the installation. Before any of the machines were disconnected all of their hydraulic tanks were pumped clean by a special purpose road tanker and a documentation of disposal was issued.


heavy machinery relocation Southampton Hampshire
Disconnection of services

The machines weighed from 500kgs to 30,000kgs. Each machine was disconnected from the mains services and where interconnections had to be split they were tagged and a detailed record made of all disconnections. Because of the size of some of the machines a detailed project schedule was produced, to facilitate access to all areas and also keep some of the production on-going. Most machines were lifted by a 30 ton fork truck as they were top heavy and unsafe on machine skates.

Once out of the factory they were loaded onto low loaders and flat beds and then transported to Derby. The machines were unloaded with a 70 tonne crane and placed outside the new site, the main door and about 2 meters above had to be removed to allow access of the larger items. Each machine was put into its correct location, refilled with oil, levelled and the main services reconnected.

Several tests were undertaken before start up:

  • Phase rotation
  • Voltage
  • Temperature

Once these tests were completed the machine was started and tested in all operations and then handed over to the customer.


heavy machinery relocation Southampton Hampshire
40 ton fork truck

Scope of work:

The relocation of a rubber mill and mixer unit, from Southampton to France.

Following our survey of the French site it was clear that the intended location would not accommodate the height of the machine. The solution was to reduce the height of the machine once in France and also to sit the machine in a pit.

The mixing unit weighed 12tonnes and was situated on a mezzanine floor, 3 metres off the floor. With no access for an overhead head lift, the machine needed to be lifted down on a fork truck. However, to complicate matters there was a large mill under the mixer, which the mezzanine floor had been erected around.

Our engineers came up with a strategy of adding removable legs to the mezzanine floor to allow us to remove the large mill. With the mill removed the mezzanine floor was marked and removed to allow us to lower the mixer to the ground safely. The mill was loaded onto a hiab lorry and the mixer was loaded onto a low loader trailer while the mezzanine floor and associated parts were put onto a curtain side lorry

Once in France the machines were unloaded into the factory via a loading bay. As the machines were going in a pit, a ramp was constructed for two purposes:

  • To allow us to install the large mill with our machine skates.
  • To allow us to drive the fork lift into the pit to install the mixer.

heavy machinery relocation Southampton Hampshire
Mill in Place

The mezzanine floor was shortened and the mixer was installed and levelled. The mill was installed once the mixer was in. Our engineers then re-connected the interconnections and site services. With the machinery ready for testing we performed the following tests.

  • Phase rotation
  • Voltage
  • Temperature
  • Flow of water

Once these checks had been completed the machines were handed over to the customer.


heavy machinery relocation Southampton Hampshire
Lift out through roof

heavy machinery relocation Southampton Hampshire
Just out

Scope of work:

The relocation of a 50 ton hydraulic press from Southampton to Ashchurch

The press was sat in a 1.5M pit and we considered several options on how to remove it from site.

Option one:
To disassemble the press into movable sections, then reassemble it at its final location. This option was ruled out due to time scale and cost.

Option two:
To lift the press out of the pit on power lifters, then lay it horizontally, to get it out of the door. This option was ruled out as it was deemed too dangerous.

Option three:
The final option was to remove the roof and lift the machine out in one piece. This option was chosen as it was low risk and kept to the time scale.

The press had all of its hydraulic oil drained and all the connection points plugged. All of the mains services were disconnected and the press made ready for the lift. A specialist, roofing contractor removed the roof then a 220 tonne crane and a 100 tonne crane were positioned outside the building.


heavy machinery relocation Southampton Hampshire
Lowering onto CAT 2 HGV
heavy machinery relocation Southampton Hampshire
Leaving the site

The 220 tonne crane lifted the press from its position up through the roof and then the 100 tonne crane hooked onto the other end, allowing the press to lay in the horizontal plane. Once in the horizontal plane a category 2 low loader was reversed under the press. The press was then lowered onto sleepers and dog chained down.

At Ashchurch the machine was lifted from the horizontal plane on the low loader, back to its vertical plan and placed in the location stated by the customer. Once in position the machine was handed over to the customer.

Scope of work:

The relocation of 5 complete production lines incorporating different types of production machinery, from Portsmouth, Hampshire, UK to Budapest, Hungary.

RJB worked in conjunction with the project team as this was a major project. We were under strict confidentiality as the planning for this size of project was colossal. We had complete control of every aspect including timescales, loading plans haulage, and health & safety.

A week before the machinery was due to shut down the auditing team completed a full audit to establish the condition of the line and take vital measurements and timings. Once the lines were shut down our skilled engineers disassembled and electrically disconnected the machinery taking care to mark all the cables and record all the disconnections. As the machinery was split they were taken downstairs via the numerous lifts ready to be packed. The machinery was vacuum sealed and fixed to pallet skids, and then loaded on to dedicated curtain side lorries. There were approximately 20 pallets in total for each line which took up space on four 40ft lorries each time.

Having cleared customs the lorries were brought onto site and unloaded in the designated area. Due to the large amount of equipment to be installed the lines were set up in two production areas located within the site. The lines were installed to the original footprint and substantial conveyors were made to carry the product to the packaging area. All connections were made and checked as well as vital timings. The lines were then ready for testing.


Static & Dynamic Checks

Static & dynamic checks carried out to check that before any mechanical parts are powered rotated or moved that they are timed correctly and will not crash.

Yellow Lining:
To prevent electrical damage, each cable that has be connected is checked in accordance with the notes and drawings by a different engineer to whom connected it.

Input/Output Checks:
To check the function of all the PLC controlled components eg, sensors, solenoids and solid state relays.

Once all of these tasks had been undertaken successfully the line had a 5 minute shakedown, to check rotation on the motors and also to see whether any of the components had come loose in transit.

After the shakedown a full 1 hour dry run was undertaken, monitoring the lines for:

  • Voltage
  • Motor & Gearbox temperatures
  • Current
  • Heater temperatures

After the 1 hour dry run had been completed successfully the line was handed over to the customer.


heavy machinery relocation Southampton Hampshire
Air Skating Autoclave

heavy machinery relocation Southampton Hampshire
Air Skating Autoclave

The job brief was as follows

Autoclave: RJB relocates 45 ton autoclave from Sittingbourne to Southampton.

The customer need to remove the Autoclave from the site in a short period of time as they had to hand the building back to the landlord, RJB came in and project managed the whole relocation.

  • Disconnect all mains services and make safe
  • Remove all components to allow the Autoclave to go through the door and also make the legal road height once on the vehicle
  • Close the door and blank all flanges
  • Electrically disconnect control cables
  • Jack and place on air skates
  • Move to main door
  • Lift with crane onto STGO3 vehicle and notify police of route and provide escort
  • Unload on new site

heavy machinery relocation Southampton Hampshire
Through the Door & No Room to Spare on Machine Skates

heavy machinery relocation Southampton Hampshire
130 Ton Crane Lifts with Ease


heavy machinery relocation Southampton Hampshire

heavy machinery relocation Southampton Hampshire

heavy machinery relocation Southampton Hampshire
Home       Our Services       Case Studies       Health & Safety       Gallery       Contact Us         Links 


Projects Southern Ltd trading as RJB Projects
Email: enquiries@rjbprojects.co.uk
Tel: +44 (0)1489 559091



machine movers Southampton Hampshire | lifting heavy machinery Southampton Hampshire | machinery movers Southampton Hampshire | transport and lifting Contractor Southampton Hampshire | heavy machinery installations Southampton Hampshire | heavy machinery decommisions Southampton Hampshire | heavy machinery relocations Southampton Hampshire | industrial machinery removal Southampton Hampshire | heavy machinery removal Southampton Hampshire | industrial machinery relocation Southampton Hampshire | heavy machinery relocation Southampton Hampshire | moving heavy machinery Southampton Hampshire | moving heavy equipment Southampton Hampshire | complete site relocation Southampton Hampshire | multi machinery move Southampton Hampshire | moving site with heavy machinery Southampton Hampshire | moving equipment to new industrial site Southampton Hampshire | crane assisted vehicles Southampton Hampshire | abnormal loads Southampton Hampshire | transporting heavy machinery | transporting industrial equipment